Programme "Transport Connectivity" 2021–2027
Priority Area: Improving intermodality, innovation, modernized traffic management systems, and enhancing transport security and safety
Duration: 28.05.2025 – 28.09.2029
Total budget: EUR 3,649,753.88
ERDF: EUR 3,102,290.80
National co-financing: EUR 547,463.08
The project envisages rehabilitation through reconstruction of an existing vertical steel sheet pile wall, located between km 491.080 and km 491.170 of the Danube River, with a length of about 87.40 m and a height of 12.70 m, included in the scope of the special-purpose port of the EAEMDR between km 491.000 and km 491.190 of the Danube River.
The reconstruction includes: construction of a new vertical sheet pile wall, combined with a concrete superstructure, anchored in the bank; reconstruction of the necessary part of the port area and infrastructure implementation of pavements, water supply and sewerage networks, lighting; major dredging of the water area in front of the wall; equipment of the quay wall with a shore-based stationary electro-hydraulic crane, mooring devices, fenders, shore-based electrical panels and fire hydrants for supplying the vessels with utilities. The rehabilitation envisages the expansion of the port territory by entering and absorbing part of the Danube River water area.
The primary objective is the modernization and expansion of the inland waterway port—a special-purpose port operated by the Executive Agency for Exploration and Maintenance of the Danube River (EAEMDR) at km 491.000 of the Danube - to enable the safe conduct of technical maritime port operations, thereby enhancing the security and safety of inland waterway transport.
Specific objectives include:
- Improving the technical and operational parameters of the bank protection structure - a vertical quay wall located between km 491.080 and km 491.170 of the Danube; its rehabilitation will ensure a new service life of at least 80 years.
- Ensuring the proper operation of berth No. 2 - located opposite the vertical quay wall undergoing rehabilitation for EAEMDR vessels at the agency`s special-purpose port at km 491.000 of the Danube. The quay wall accounts for approximately 46% of the total quay frontage of the EAEMDR port. The new quay structure will withstand increased horizontal and vertical loads, addressing areas where the safety factor was previously reduced. Upon commissioning, the rehabilitated quay wall will be operated under public management by the EAEMDR. Only non-commercial activities will be carried out, with the port - including the quay wall—constituting public state infrastructure.
Project Activities:
- Project Preparation and Management, Implementation Monitoring and Reporting
The activity covers the organisational, technical and administrative tasks required for the successful implementation of the project. These include the preparation and coordination of project documentation, conducting procedures for the selection of contractors, obtaining the necessary permits and approvals, as well as monitoring and supervising the construction works until the completion and final acceptance of the site.
- Engineering Services (Design, Construction and Author`s Supervision)
The activity includes the preparation of the necessary design documentation, carrying out preparatory works and implementing the construction works related to the reconstruction of the existing quay wall on the Danube River. It also covers the provision of author`s supervision, as well as the completion and handover of the reconstructed facility.
- Consultancy Services (Construction Supervision, Management and Coordination of the Construction Process)
The activity covers independent supervision of the design and construction processes to ensure that the construction works are carried out in compliance with applicable legislation and quality requirements. It includes monitoring progress, checking the materials used and the works performed, coordinating the construction process and providing assistance during the acceptance and commissioning of the facility.
- Information and Communication
The activity aims to ensure the visibility of the project and the contribution of the European Union to its implementation. It includes the production and distribution of information and promotional materials, the organisation of opening and closing press conferences, and the publication of information on the project`s progress and results.